Regarding certificate from vendor

Former Member
0 Kudos

Dear Gurus,

Please advice for the requirement

Whenever material is received from vendor accompanied with certifictes of vendor it should go to unrestricted stock although inspection is active

if stock is received without vendor certificate , it should go to quality stock and inspection lot to be generated

This is with respect to both approved and non approved vendors

Please suggets

regards

Venkat

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member211618
Contributor
0 Kudos

Hi,

   This scenario can do by using Vendor certification process,

You have to enter the Target QM System by activating the QM procurement Key & maintain the Existing QM system in Quality info record with valid to date.

While doing the GR creation for relevant certified vendor system does not create the inspection lot even if inspection type active (stock move directly to Un-restricted).

Former Member
0 Kudos

Hi,

Explore below mentioned IMG path-

Quality Management->QM in Logistics->QM in Procurement->Define Keys for Certificate Processing

In this under Difine certificate types, explore field-"Control without certif."

Regards

Vivek

former_member207800
Active Contributor
0 Kudos

As I remember... if stock is received without certificate, it goes to blocked stock automatically.

But inspection lots will be created for both situation. (different system status of insp. lot)

So please test your scenario without "post to insp. stock".

Sorry. I didn't test.. so my answer can be wrong.

Regards, DoWook KIM

anand_rao3
Active Contributor
0 Kudos

Venkat, I don't think this could be feasible without any enhancement!

AR