on 11-02-2012 5:39 AM
Hi All,
I have created one PR through PS module and after some time i have changed that quantity in CJ20N and saved that. After that whenever i m checking same PR in ME53N it shows old quantity.
Please provide me the solution for the same.
Hi PS,
Check whether the changes are reflecting in Environment Tab when you open the PR in CN53N.
Regards,
MRD
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please confirm when you make changes in PR qty in CJ20N in one screen, are you immediately trying to look change of qty in PR in ME53N in another screen. If so, changes will not be reflected immediately.
I have just tested like as mentioned below and it worked for me.
1. Change qty of PR in CJ20N. Save this.
2. Open another screen and execute ME53N transaction by entering the PR number.
3. New qty changes is reflected in PR.
Regards
Tushar
Hi,
This looks some inconsistency.
Have a look on SAP Note 741168 - A Report to link Network acts to Purchase Req.
Else you can raise this issue to SAP.
Regards
Tushar