on 11-01-2012 1:49 AM
Hi PS Experts,
I have 1 simple question as follow.
I understood I can charge the costs in WBS. The cost can be finally settled using tcode CJ88.
[Example]:
Settlement
________________________________
Cost Center 100 | WBS 100
Here is my question. If the project also generate some income (Revenue).
We also post both revenue and costs into the WBS like below.
Cost 100
Revenue 120
Net 20 then what will happen when I run CJ88 to settle WBS?
1. Cost -20 will be posted into Settlement Cost center ? (Net)
2. Cost 100 will be posted into Settlement Cost Center? (Revenue is just ignored)
Thank you in advance for your kindly reply!
Best regards,
Check with your CO consultant, whether CO-PA has been implemented or not?
If yes, then you settle your revenue generating project to PSG.
If not, ask them where do they want to settle the project?
Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Amaresh and all,
Thank you for all your valuable inputs.
So, give me final answer. Anybody who answer my query with closed end answer will be marked as answered.
1. CJ88 cannot settle revenue (Correct?)
2. Since we are activating COPA, revenue will automatically settled to COPA when biilling doc is posted.
Thanks!
1. CJ88 cannot settle revenue (Correct?)
It can settle revenue, provided you give correct settlement receiver. In this case it is Profitability Segm
2. Since we are activating COPA, revenue will automatically settled to COPA when biilling doc is posted.
If you activating COPA, then It'll get settled the moment you run CJ88 (It could be either manual or you can schedule a background job).
I'm sure you are running RA (KKA2) to determine the cost of sales, revenue etc... before running settlement.
Regards,
Amaresh Makal
Hi Jiro,
Agree with Amaresh...
In customer project, usually result analysis is carried out before settlement.Settlement settles only those objects for which result analysis has been carried out.
Result analysis calculates revenues by period along with balance & reserves and settlement will settle the values that is determined to a settlement receiver (usually it is profitability segment) if COPA is activated.
If the revenues affecting the result is different from actual revenues, then difference will formed either revenue surplus or inventory from which revenue can be generated depending upon whichever amount is greater.
In addition please also refer below thread discussed on scn showing WBS settlement approach when PA is not activated.
http://scn.sap.com/message/9897111
Regards
Tushar
Tushar,
Hi, Thank you for your supplementrary information.
I am not sure if we are using Result analysis key.
What I don't understand is that When we post revenue, since we define default PA segment in
OKB9, the revenue will be automatically transfered to COPA even if we put WBS element as cost
object. If WBS and PA are there in billing document, is WBS posting become statistical?
Or COPA become statistical?
Sorry if I am asking silly question. Please allow me as I am not familiar with PS module.
Thanks
Agree with Mahendra - I think you should be settling to profit center or profitability segment.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think it will be better if you try youurself and share results with us!
I think revenue settlement to cost center is not possible in std SAP,so it is likely that it will follow step 2. However please check with CO consultant for more information.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.