on 10-30-2012 1:29 PM
Hi,
We have recently configured a new location with work areas and propagation ranges and for the same the orders are not moving inside the planning board.
When ever trying to move the orders, it is showing with "Error in Rescheduing logs" and with no valid modes available for a particular activity.
Any particluar reason for the same or do we need to activate some settings for new created location for planning board?
Thanks,
Prash
Hii Prasanth,
Did you able to get the Root cause ? Your problem has been resolved or not ?
Regards
Debashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No Valid Modes, Means PPM/PDS has not maintianed properly. Check The same, after that maintain Infinite schduling in startegy profile and then try ....
Debashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The issue was due to wrong capacity planners in resource.
Prash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.