on 10-29-2012 3:32 PM
Hi
Need your help to figure out a standard solution for the following problem:
My client has a situation where Goods are receiving time varies as per the source location and also the receiving day is different as per the source location.
Can we handle this so that Heuristic can consider this for POs and PReqs as well.
I understand with Transportation Shipment scheduling we can have Unload condition type and also the transportation calendar on TLane can help but it doesnt get considered for PO and PReqs by Heuristic.
Kindly suggest
Thanks in advance
RK
Hi R K,
BAdI /SAPAPO/RRP_PLANNING may be considered.
Best regards,
Tiemin