how can I release job so that it runs every day except on sunday at 14'o clock

Former Member
0 Kudos

Hello

I wander how can I release job so that it runs every day except on sunday at 14'o clock? In sm37 I do not find such option

Thank you in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello jan,

That would not be possible in sm36/37,

solution :

1) it could be achieved through SAP Redwood CPS/Cronacle tool.

or

2) workaround would be , define 6 weekly jobs (monday through saturday)

thanks

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Jan,

You can use the restrictions tab in SM36 which has option to skip the job on sundays, we use this to skip a job to run on Sundays in one of our system.

Below is our selection to achieve this,

Hope this helps you.

Regards,

Pradeep

Former Member
0 Kudos

hi Pradeep,

using factory calendar would add the job , not running on holidays according to the calendar defined.

correct me if i am wrong.

Former Member
0 Kudos

Hi Nikhil,

Yes, it happens if you have holidays defined in your selected calendar, or else the job will not run on Sundays. You can define a test job and check in any sandbox.

Regards,

Pradeep

Former Member
0 Kudos

Hi Pradeep,

Thats what the original question was.

mon-sat > job run

sun > skipping it.

and problem with factory calendar is :

suppose if monday or say Wednesday is holiday as per your calendar, then job would get skipped on those holidays too, instead it was intended to skip only on sunday's.

@jan : Are you able to get this resolved.

Former Member
0 Kudos

Hi Nikhil,

We can have a calendar i.e. not defined with holidays. The selection shown above help us to run our job on all days except on sundays.

Former Member
0 Kudos

Hi Pradeep,

workaround is on you what decide to go for.

i suggested to avoid moving a TR if you create a factory calendar.,

and its not client specific too.

Thanks