Hi,

I have a scenario running in Prod. I found that the values of the MM lets say a field "isActive=True" after the MM in sxi_monitor.

But when I verified the same message in RWB, the same "isActive=Active". Was wondering where is the provision to make changes to the xml after the MM is done? throw some light, experts,

Venkat.

Accepted Solutions (0)

Answers (1)

Answers (1)

MichalKrawczyk
Active Contributor
0 Kudos

hi,

you can change the values in message mapping but you can have many of them in the operation mapping, you can change them in mapping in ccBPM - in a transformation step of before the ccBPM, you can change the values in adapters (by invoking the mapping from the adapter module) so there are many places but they should all be clearly visibile in monitoring steps