on 10-25-2012 3:57 AM
Hi all,
I have a situation here where someone is able to complete and close the Quality Notification (NOCO, NOTI and ATCO) even when 1 of the task in the items tab is in the status "TSRL".
May I know why is it possible?
Usually a Quality Notification can only be closed when all tasks are in "TSCO" status.
Is there any way or method where one can by-pass it?
Thanks for all the advise.
hi
i think it is not possible to close the notification before ALL the task is completed. whether it is occured for one particular notification or type or all the notification.;
if all the notification then some one has changed the system status control in BS22 for outstanding task
kindly check
Regards
Thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.