on 10-24-2012 11:06 AM
Hello experts,
Some of the docs i have seen on how source determination happens in PP/DS says that "If several sources of supply (PDS/PPM) has the same priority, the system considers the one lowest cost". I can see that we have a cost field in PPM, and in SNP-PDS. I dont see a 'COST' field in PP/DS PDS. So is this valid for PDS by any chance?
I am wondering if the docs are i read are correct or if i am missing something. And moreover does the normal heuristics consider cost as a parameter? i thought 'cost' effects were a matter for optimizer only.
Helpful answers will be heavily rewarded
regards,
Sreeram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
cost in the PDS will only be used by heuristics to rank possible sources of supply (together with priority, on-time delivery...) and then select following this rank. This decision depends only of this particular product and the current plannning situation, there are no trade-offs.
The optimizer will compute a global cost for selected products combining makespan, delays... but it will not use the cost in the PDS. If I remember correctly, the PDS cost is at header level, and as the PP/DS cannot change PDS for an existing order, all PDS costs are a constant for the optimizer and do not affect the result. Never tried the option of creating PP/DS with the optimizer, in that case I assume it would affect the result.
regards,
J.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.