on 10-23-2012 3:04 PM
PR is created by MRP.
Planned Delivery Time: 4days (calendar date. right?)
GR Processing time : 1 day (working date. right?)
PR : 10067822
Planned date : 01.11.2012
Delivery date : 31.10.2012 (Planned date - GR processing time)
Release date : 27.10.2012 (Delivery date - Planned Delivery Time)
=> no problem.
PR : 10067823
Planned date : 02.11.2012
Delivery date : 01.11.2012 (Planned date - GR processing time)
Release date : 27.10.2012 (Delivery date - Planned Delivery Time) => I can't understand. I think release date is 28.10.2012. PDT uses calendar date.
Is there anyone who knows?
Hi Hye-young,
Is 27.10.2012 a working day or not? I guess it is, but 28.10 isn't.
You're right that PDT uses calendar day. On the other hand, releasing PR has to be done by someone in the plant so it has to be a working day. The 2nd sample makes sense to me.
Best regards,
Tiemin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.