Manual capacity determination for work center

former_member232086
Participant
0 Kudos

Experts,

  How can we set the capacity for the work center manually in SNP? We have one wok center for which the capacity is based on the total man hours ,ie, for this month our capacity for work center "X" is 1000 hrs but in SNP is 720 HRS which is 30*24.Can we change it to  1000hrs only for this work center?

Pls advise,

Regards,

Vijesh

Accepted Solutions (1)

Accepted Solutions (1)

former_member197994
Active Contributor
0 Kudos

Hi Vijesh,

In resource master data //RES01, go to capacity profile, change the utility rate to more than 100%

and save, I can see that the bucket capacity is adjusted accordingly.

Best regards,

Tiemin