Not able to schedule the Project

0 Kudos

Hi All,

While Scheduling the Project using Tcode CJ20N getting the message" Network contains loops and cannot be scheduled". and i have checked that loop analysis also  it is showing no loop exits.

Please help me to provide the solution for the same.

Thanks in advance.

Accepted Solutions (0)

Answers (5)

Answers (5)

sanjeevc
Active Contributor
0 Kudos

Hi,

check relationship is maintained for all activities in existing structure. once you maintained those then directly you can schedule activity by CLT F9 commend.

Basically loop issue come due to not maintain proper relationship between activities.

Regards,
Sanjeev

0 Kudos

Did you get the solution for the same....

I have facing the same error,

Regards,

former_member201206
Active Contributor
0 Kudos

Hi,

is there sub-networks involved, which typically cause the unwanted cycle. As far as I remeber, you can enter the main-networks and then include sub-networks.  And ussing select all to select alls the nodes in network-view.. Somewhere in the menu there is option to let the 'hidden' relationships generated. Then do the loop analysis again.

Genearlly do not maintain any manuall relationships between main-activity and activites in sub-nets.

Kind regards,

Zhenbo

0 Kudos

Hi Zhenbo,

Thanks for your response .

I have checked and found sub network is available and whenever we are giving the relationship between network and sub network getting the message "Network contains loops and cannot be scheduled".

Please guide me how to correct this issue.

Thanks in advance.

former_member201206
Active Contributor
0 Kudos

Hi,

as I said before, DONOT maintain any relationships between activity of main-network and activity of sub-network.

The program will automatically generate relationships according some rules for sub-network during the scheduling.

As I remember the rule are following:

Every relationship the main-activity has, on which the main-activity is the sucessor, then each activities of the sub-networks without predecessor copy this relationship.

The anlog logic for the main-activity is the predecessor of a relationship.

It sounds complicated, but you take some time to think about, it makes sense.

Kind regards,

Zhenbo

Former Member
0 Kudos

Hi Neha,

Try to reset loop analysis once and re-execute

Edit ® Functions ® Loop analysis ® Proceed.

Please refer help sap link below

http://help.sap.com/saphelp_470/helpdata/en/4c/22623c46e611d189470000e829fbbd/content.htm

http://www.consolut.com/en/s/sap-ides-access/d/s/doc/YV-CN611

Regards

Tushar

0 Kudos

Hi Tushar,

Thanks for you support.

I have done the changes as guided by you but still the same problem is coming.

Please help.

sunil_yadav2
Active Contributor
0 Kudos

try to schedule manually and then check.

Former Member
0 Kudos

Hi,

Please check if following SAP Note can help you.

Note 151551 - Consulting : Scheduling of Network

https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=151551

Regards

Tushar

former_member195427
Active Contributor
0 Kudos

Hi,

    Kindly Follow the given path and let us know if it worked;

  1. Call up the network structure graphic.
  2. Select the menu options Edit -> Functions -> Loop analysis -> Execute.
The relationships causing the loop are highlighted.
  1. Choose new relationships between activities so the loop no longer exists.
  2. Select the menu options Edit -> Functions -> Loop analysis -> Execute.
The relationships are no longer highlighted.


Regards

Ankur

sunil_yadav2
Active Contributor
0 Kudos

Dear Neha,

Please whether the relationship is correctly maintained or not. this means if a relationship exist and at last relation comes to same activity this will lead to Loop.

like 1-2-3-4-1

please also check as below:

Procedure

    • Call up a network or standard network in create or change mode.
    • Choose This graphic is explained in the accompanying text.
    The network graphic appears.
  1. Select the menu options Edit ® Functions ® Loop analysis ® Proceed.
  2. Relationships that cause a loop are highlighted in color.
    • Select the relationship that causes the loop.
    • Choose This graphic is explained in the accompanying text.
    The relationship is deleted.
  3. To deselect a loop, select the menu options Edit ® Functions ® Loop analysis ® Reset.
  4. To return to the standard network or network, press This graphic is explained in the accompanying text .

Thanks

Sunil

0 Kudos

Hi Sunil,

i have done that and it is showing "No Loop Exist" but while scheduling the Project I am getting this message "Network contains loops and cannot be scheduled".

Please help.