on 10-23-2012 4:28 AM
Dear Experts,
We have a parent WBS A and it have 5 child WBS. And in our current scenario we have assigned & released the budget at parent level directly(as per top-down planning approach).
But Now our business requirement is to distribute the budget of parent WBS to its child(i.e. bottom up approach) as it will be easy to monitor the budget. I have distributed the budget of parent WBS to its child using CJ30.
But at the time of releasing using CJ32 it gave me the error "Over all release is less than distributed release"
So is there any way for distributing the released budget to child level after some procurement. Please suggest if it can be possible.
Note: There is also some assigned budget in CJ32.
Regards
Shishir
Dear Srivastva,
Please check whether you have procurement at top level WBS if yes than this will not allow you to reduce budget less than procurement. otherwise you can change the budget according to you.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunil,
Firstly thanks for response.
Yes we have done some procurement at top level WBS.So According to rule it will not allow to distribute.
But If we add-up some extra budget(as equal to procured amount) to the budget to be distributed at each of its child and then perform total up, then could it be possible?
Regards
Shishir
Dear Shishir,
if you have made procurement it means you have consumed you budget at top level so its not possible to remove that amount.
like budget of top WBS -10000
procurement - 5000
so you can able to remove/ distribute only rest 5000 to lower levels.
So if you require to distribute to lower level more than 5000 so you need extra budget for this.
L1 WBS-12000 (Bcos 5000 is already used for procurement so distributable is only 7000)
L2 WBS-3000
L2 WBS-4000
Thanks
Sunil
yes you right assume sense of budgeting if you are using budget distribution from single window then you continue your process.
as total up budget is 1 lac
you can consume 1 lac at any level as child wbss.
in case your system tolerance limit is more then 100% as 105 with that setting you can use 5% of total budget. but activity type should not be assign as 3 = Error message
Regards,
Sanjeev
Hi,
Whenever you use total up, error message will occur during saving. You have to keep this in mind throughout the life cycle of project. If you can release 100% then there is no issue.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Avoid the use of Total Up. Do manual calculation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Shishir,
if you have created PR using ME51N so only you have to do is change account assignment to next level WBS.
If you have assigned material component to WBS than drag and drop to any other location or other WBS.
Note: this is possible only when you are drag n drop within same Network. Not allow in other network.
Please check.
thanks
Sunil
Hi Srivastava,
In case if you have raised indents on higher level then try to move the assigned networks to child WBS. Try this in quality server first.
Along this I just want to inform you that budgeting on lower level will lead to better control but less flexibility. So analyze pros & cons before moving. Besides this It is not advisable to change budgeting level after transaction.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.