on 10-22-2012 5:21 AM
Hello All,
We are having four plants in our ECC system. Out of that only one is APO relevant. Rest other are not required in APO.
My question is how can I transfer only one specific plant to APO system?
I didn't find selection for plant in CFM1.
Is there any user exit required to map this requirement?
Thanks
Manoj P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As mentioned by DB, integration models(IM) are used to constrain / restrict your options. You can also save an IM as a variant and re-use it for repetitively. These variants will be useful for scheduling a job for repetitive processing.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.