BBP_GET_STATUS_2 log

Former Member
0 Kudos

Hi experts,

We are on SRM 7.02.  BBP_GET_STATUS_2 programm is running as per sap note 1145063. But sometimes documents (SC) are not updated, so we execute report for particular cart and it gets updated. What a possible reasons for this issue? And are there any ways to monitor this failures?

thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

any updates guys?

former_member208675
Active Contributor
0 Kudos

Hi,

Take a look at SAP Note 1495231 - BBP_GET_STATUS_2: Performance improvement. It may hope you in this case.

Regards,

former_member208675
Active Contributor
0 Kudos

Hi,

What is the time interval between scheduled job? Try to keep it as less as possible.

Then you don't need to execute particular report manually.

Regards,

Former Member
0 Kudos

Variant 1: Last 2 days ; Job executed every 3 minutes

Variant 2: Last 30 days ; Job executed every 30 minutes

Variant 3: Last 180 days ; Job executed every 4 hours

P.S. sometimes carts are not updated even after 1 week

Former Member
0 Kudos

Hi Morgan,

Do any of your job is getting stuck or lock out? Can you check that out. Because the way you have set up variant 2 and 3 to execute every 30 min and every 4 hours. During that time Variant 1 job also execute and lock out the records.

Please refer to following SCN to set up job http://scn.sap.com/message/1831557#1831557

Hope this helps.

Thank you

Ritesh

Former Member
0 Kudos

I've checked in SM37 - all jobs in "Finished" status, so as I understand no locking occurs.

are there any ways to monitor this failures?