on 10-17-2012 10:41 AM
Dear Experts,
working on a blueprint/design phase with SCM7.0. My question is there anyone out there that can provide a clue for the following:
1. I am executing deployment with an ATD quantity (let's say AT1) of Stock and Production order
2. Want to execute TLB,however require the ATD quantity to be for group AT2 stock only. As with all things, this is a requirement from the client.
My investigations so far, have not been fruitful,in that I cannot complete above via any configuration settings.
So can this be done via a user exit? any insight would be useful.
Paul
Paul,
Is your client requirement to use one ATD for deployment and one for running TLB? and you are you running into conflict because system allows on location master, only one choice. Have I got the question?
regards,
Najam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.