on 10-17-2012 7:12 AM
Dears,
I need to change the financial, capacity planning start and end date to all the buckets to 01.01.2013 - 31.12.2013 under a portfolio. Currently it seems that the changes made to the portfolio date do not get ripple down to buckets under it. Dates need to be modified each and every bucket then. There are more than 100 buckets in our portfolio.
If it has to be done manually, will consume a lot of time. Is there any way to automate it?
Regards,
Anirudhdha
Hello,
You can use this transaction RPM_DX_BUCKET. You only need complete the excel file ( bucket tab) and upload it in change mode.