Visibility of 'delivery completed' flag on purchase order in SNC browser

Former Member
0 Kudos

I am using SNC 7, in particular the PO collaboration scenario.

In the connected R/3 4.7 system I have flagged a PO item as 'delivery completed'.

But I do not see this flag on the PO item when viewed via the SNC browser.

Can anyone advise me here?

Thanks...

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Group APO,

The "Delivery Comnpleted" indicator on the ECC PO does not flow automatically to SNC beacuse the ORDCHG Idoc is not trigerred when this indicator is set. You will have to develop a custom solution if you want to trigger the Change Idoc.

Please refer SAP Notes # 865778 and # 846721 which discusses this item.

Regards,

Bharath

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Group APO,

Scenario 1

Did the PO undergo full SNC cycle like PO-->Confirmation-->ASN-->Good receipt --> Delivery completed in ECC

OR

Scenario 2

You forced Dlv complete on the PO line item.

In Scenario 1 & 2 , the Item status will have Delivery Completed.

There are no separate Flag in SNC.  Hope this helps.

Thx

MJ