0 Kudos

We are using cost element planning for our projects.  We use CJR2 to plan revenue and costs at the WBS/cost element/period level.  Currently we use a CO version, not plan 0.  I would like to make these costs and revenues appear on CN41N, along with the actuals.  Is there a way to do that?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Yes, you can do it.

Instead of CN41N try to use CN41. Execute CN41, go to Settings, choose Value Display and then Plan Versions. Choose the plan version where you saved your planning data for costs and revenues.

This should give you the required output.

Hope this helps.

sanjeevc
Active Contributor
0 Kudos

yes system will allow for doing this, but you have to compare your data with budget basis like budget vs. actual in cns41.

you need to copy plan version 0 and rename and un-check plan object then when you do plan in cjr2 then use version whatever you created without check  mark plan. you will get your result.

Regards,