on 10-11-2012 2:02 PM
I have a situation, where the delivery was created in the august and goods issue date was also in the august, goods were picked, but goods issue was not carried out. now when the users want to dot eh goods issue, system cannot process further, becuse of the posting periods have been closed.
tried to change the goods issue date to current date to complete it, but it gave this error :
Message no. L3124
This delivery does not contain any open items that require picking.
This can result from the following conditions:
but there was no link to the warehouse. could you all please suggest me how to complete this delivery.
thanks in Advance
but there was no link to the warehouse
Do you mean to say warehouse is not implemented ? But the error says, the issue is related to warehouse and you need to check the following note:-
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.