Hi Experts,
When am processing PO, am getting the following error
" Item 1002 WBS element PPO-000057 budget exceeded
Message No : BP603 "
In CJ32 screen I updated the budget figures
after that I executed CJEO / CJEN
but still its showing the same error message.
Regards,
Sanju M S
Dear All,
it gave me the same error while releasing the billing document.
Regards,
Sanju M S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanju,
Please check the report S_ALR_87013558 and check the available budget for the same year for which you have released your budget. If, the budget is not there then supplement it.
Supplementing required budget should definitely resolve your issue if you have followed the above posts properly.
Regards
Ankur
Hi Sanju,
To post supplement budget use transaction CJ36, CJ37.
You may also transfer the budget from WBS to WBS using t-code CJ34.
To return budget from WBS use t-code CJ38.
Also, keep track of available budget for these postings from S_ALR...558 report.
And to view budget updates(transfers etc.) use report S_ALR_87013560.
Regards
Ankur
Sanju,
Looks like, without reading SAP help/ training yourself, you are trying to configure the system.
I have gone through the entire thread. This kind of issues have been discussed many times in the forum. Simple search will help you and save many forum members time and effort. Please get trained/ read. Post some quality questions.
Dear fellow forum members/ Friends: Don't mistake my words. Lets not get in to a race to accumulate points. Lets bring in some quality content to this forum. Hope you all understand.
Kind Regards,
Amaresh Makal
Hi Sanju,
This error come generally due to following reasons:
Regards
Ankur
Hi Sanju,
Go to OPS9 and check 'Activation type' under Availability Control is Active for your Budget profile.
If it active, follow steps mentioned below.
1. Deactivate availabilty control : CJBW
2. Refresh Project database : CJEN
3. Activate availabilty control : CJBV
Once you complete this, try proceeding with PO.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Sanju,
Apart from above.
Message setting configure to restrict purchase order creation if it is exceeding Budget value!
use OBMSG / OBA5 tcode for application area BP for message number 603 and set as warning instead of error but check with business guys after then you can proceed.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanju,
If the error that is being displayed is valid, why do want to change the behaviour of the system? Firstly check why the error is being issue. Is it because of insufficient budget?
Supplement your budget, if needed, in such a case and go ahead with your transactions. Check the reports suggested in the previous post.
Always try to find the root cause of the error before going for any alteration in the standard system behaviour.
Regards,
Gokul
Hi Sanju,
It has been discussed so many times in forum.
Please search.
However have you checked s_alr_87013558 & S_alr_87013560. Check requirement date and availability on that date/FY.
If error message is absurd then run cjen then cjbn with budget profile selected one by one.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.