Dear All,
I am working on a scenerio which is related to production on project. I am creating sales order through which system creates project via assembly process. After releasing of project i create a production order for a finished good via CO10 on WBS element and this finished good has 2 BOM item inside, one stockable item and another one is non stockable item (Non stockable is procured every time via vendor).
After releasing of production order system generates PR for non stockable item which comes in MD04 and later on we convert PR into PO and do the MIGO process. Also we confirm the productoin order with goods movment of stockable component.
After final confirmation of production order i can see delivery quantity in production order, also if i run the report MMBE, it shows me project stock of finished goods.
Now when executing transactoin CNS0 for delivery of finished goods via project, system is fetching non stockable component (Raw Material) and not finished goods even though i can see in reports project stock of finished goods.
I gone through best practice document for ETO and same steps but now i am not able to deliver the finished goods via project.
Please help.
Thanks in advance.
Hi,
In addition to above suggestions given by Sudhakar & Sunil, please check following.
1. Check whether non stockable component is marked for deletion.
2. Check if requirement quantity is not negative.
You can watch out at below constraints when doing Delivery from Project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear PM,
Please check whether finished good which is assigned to project is checked for backflush. if this is checked than this material wo'nt show in CNS0.
Hope this will solve your problem.
Thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Which shipping location is was stored? that also very important while doing CNS0.
You can see it in MB52 to find out the which wherehouse location. After production confirmation, does goods issued to project.
Regards
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.