Hello All,

I have a complex scenario regarding Planning Delivery Schedule in Sales. We are doing MTS scenario.

We assign Pouring Pumps for customers in Advance . For example

Customer         Material    Quantity     Location    Time     Customer No

(PUMP-50)

ABC                Cement-1   200M3        Site-A      6:00AM    123

Now when i tried to do in sales order in schedule line my client rejected. they says they want detailed planning for Pumps. I am looking for the solution. Below is the screenshot

Best Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

siva_vasireddy2
Active Contributor
0 Kudos

Hi,

   Please can you Brief in Detail of the Requirement.