on 10-07-2012 8:24 AM
Dear Sap Experts,
Is It Possible to do UD for each operation of an inspection lot generated through Production Order (Inspection type 03). please help me.
Hi,
In SAP, for operation completion, you can use the following settings:
You can use IMG activity to define the combination of inspection type and plant for which the operation completion is to be allowed.
Path is : Quality Management --> Quality Inspection --> Result Recording --> Make settings for Operation Completion.
Regards,
Sumit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry.. UD for operation is not possible.
Only valuation for inspection point & UD for inspection lot are possible.
Please refer the inspection point concept, you can valuate each operation using this functionality.
Regards, DoWook KIM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To fix my wrong answer..
As Sumit Gupta mentioned already, there is new functionality from ECC EhP.
For more information please refer below link.
http://help.sap.com/erp2005_ehp_06/helpdata/EN/c7/952642aaf1de2ce10000000a1550b0/frameset.htm
Regards, DoWook KIM