I've configured availability check at sales order, but when I create a sales order by 10 units the system confirms zero , the stock ( free) is 1.000 units.
Any idea about this issue.
Thanks
Hi,
When you check whether you have available stock to confirm a sales order, you should always check in transation CO09. Only CO09 gives a real view of ATP situation. See note 123500.
You may also verify your ATP checking scope in transaction OVZ9.
In addition, run report SDRQCR21 in simulation mode to make sure there is no inconsistent requirement entries occupy the available stock. See note 25444.
Claire
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
check that u are getting plant at item level.. and check whether any delivery blocks is assigned at order level and at schedule line level.. and if it persists.
Run the Program SDRQCR21.. Give Material, Plant and execute.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jaime,
With all the inputs from various member I think now the problem has been resolved.
Thanks,
Suman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Suma,
Really not, I 've checked and checked the setting , but something is not working:
CO09 displays Stocks :460 ; Cust.orders : 310 = confirmed issues = 310.
I need to set up the next behavior: If I create a Sales order by 350 units, the system
only should accepts 150 or less ( 460-310) , but now is confirming ZERO, moreover if I enter 10 confirms Zero again..
The Availability check in material is 02 ( Individ.requirements)
VOV6: Sched.line cat is CP ( Req/assambly and Availabilty are checked )
OVZ0: I' m using 031 as requirement class
and in Sales area for availabity check is C (delivery proposal)
Is there more configuration should be revised ?
Please your advices
Thanks
HI Jamie,
Check MD04 Transaction. If any other order / Delivery is blocking this stock.
Please increase the stock to check, whether your configutation and Master data are correct or not.
Regards
Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jaime,
You can check the schedule line configuration whether 'it has been activated for availability or not'
You can also check that, which plant you maintained in mmo1 as well as procurement type.
as this kind of check is carried out by system at ATP/Plant level, so something must be there changed in configuration point of view.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You need to check the stock availability using transaction code CO09. Also check material master MRP views to see whether any safety stock is maintained or not.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jaime,
Can you check that in Material Master Sales General Plant data tab the Availability Check "02-Individual" is maintained or not.Also check that Delivering plant exists in the Sales order or else you can maintained it in the Material Master itself.
Thanks,
Suman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.