SLD Syncronization PROD to QA

AntonioSanz
Active Participant
0 Kudos

Hi all experts,

     I have an SLD environment with 2 SLD, one for QA and other for PROD. I want to define transport target in SLD QA, but I dont have defined there the PI PROD Integration Server.

     I want to register SAP PI PROD into SLD QA, but I find that this configuration is a bit complicated. I want to ask you if I can copy the content of SLD PROD to SLQ QA but I dont want to lose all the information in QA. Doing that I think I will have SAP PI PROD Integration Server in SLD QA.

Is that posible?

How can I do it?

Many thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

I guess u might have already seen this link:

http://help.sap.com/saphelp_nwpi71/helpdata/en/46/2f42f114bc59bde10000000a155369/content.htm

Yes, u can also manually transport the SLD objects but in case u want to deal in safe manner take the back up of entire SLD.

Thanks

Amit Srivastava

Former Member
0 Kudos

Hi Antonio,

You need to create group in SLD for registration/  transportation.

Also, you need to define the target Business system in the Business system that will identify to which system/environment the objects are transported.

Ref: http://scn.sap.com/people/rajasekhar.reddy14/blog/2011/02/21/transport-targets-and-groups-in-the-sld