on 10-04-2012 11:33 AM
Dear Experts,
I have involved in QM/PM implementation project and we tried to use follow-up action to create notification after UD at inspection point but it doesn't work. Is there any way to activate follow-up action after we enter UD code (rejected) at the inspection point.
Thanks & regards,
Suppawat
Hi,
Assign the follow up action created to the UD code in the T.Code : QS51.
Regards,
Sumit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am not sure what steps you followed but ,
1.Create a Z function module which will
- include code for creation of notification
refer : http://scn.sap.com/thread/1471778
or
- use bapi's like
BAPI_QNOTIFICAT_CREATE
QM05_CREATE_NOTIFICATION
2. In std sap QCC3--->Inspection lot completion--->Define Follow-Up Actions-->Follow-Up Actions
use Z Function module above created.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.