on 10-04-2012 10:34 AM
Hi Gurus,
We see a strange scenario where Heuristics is planning only for Distribution demand and not for forecast when we run this through proces chain. If we run the same heuristic inercatively or through background job in SM37, it does plan for Forecasts too. Is this a bug or we missing something. We are running Location Heuristics for a selection ID that has around 500 Loc-Prods. This is one of the steps in a proceess chain.
Thanks,
Vanshaj
Hi Vanshaj,
You may need to redetemine the low level code in /SAPAPO/SNPLLC.
In addition, please check if you have other steps are excuting at the same time in the process chain. If so please check the data selection has overlap.
If you are using parallel processing profile. you may remove it then run the planning again.
Claire
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.