Assigning different work centers to people for an operation

Former Member
0 Kudos

I have to assign different people with different activity rates to my operation .

I have to click  the split creation function role in partner and thereby activate the requirement assignment tab.

Can I also assign my work centers to each person in the requirement assignment tab?

This is because I need to maintain different activity types to each person performing that operation.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

hi

you cannot able to specify the different work center for the same operation.

also you cannot able to assign workcenter in requirement assignment tab

what you can do is specify 2 operation with the same operation and manually change the activity type to the required one

regards

thyagarajan