on 10-02-2012 12:39 PM
hi
I want to create a milestone for a project.
Is there a way to create a milestone under an ACTIVITY ( the activity is under WBS ).
thank you
Ami
HI,
Ist method :you can create milestone at wbs and activity as well execute cj20n and drag milestone and put to assignable object i.e. wbs/activity where you want to create milestome.
IInd method : in cj20n click on wbs/activity then click on milestone icon define uses and required information then save.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just drag and drop the milestone on the activity in the project in tcode CJ20N. Enter the details for the milestone. Thats how you create a milestone in the simplest manner.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ami,
Yes, you can create Milestone under an ACTIVITY.
Milestones are created manually in Project builder or by copying from a standard milestone.
Milestones are assigned to individual WBS elements or activities.
They can be used in both in operative WBS and standard WBS.
Please refer more on help.sap at below mentioned link
http://help.sap.com/saphelp_46c/helpdata/EN/06/18b22672dc11d1a57b0000e82de7c3/frameset.htm
Also refer below thread
http://scn.sap.com/message/13535519#13535519
Hope this helps.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.