on 09-28-2012 7:17 AM
Hi,
I encounter a problem which system automatically changes the availability date/time in the production order.
Example,
Material A , production order released to ECC on 27.09.2012 at 13:44:23.
On 28.09.2012 at 10:52:27, the production order scheduled start time, finish time and scheduled finish date changed.
Is the system automatically changed the availability date/time for material A production order due to requirements from higher/lower level components?
Even the production order status is REL, availability date/time still can changed?
All the materials set as planning procedure 4, planning in planning run.
The materials did not set as planning procedure 3, cover dependent requirements immediately.
Or the changes due to heuristics setting SAP_PP_001 (/SAPAPO/HEU_ORDER_CHANGE)? Can I remove the heuristic?
Please advice.
Hi Yee Ting,
You can check the PO's "administration" tab to see who the changed user is.
If it's a CIF user, then something done in APO can be the reason. You can turn on detailed log to
find out more.
Best regards,
Tiemin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tiemin,
I have new sample to check, production order X in the 'administration' tab only show changed by 'RFCUSER' (CIF user).
In APO logs, the logs show that user X have changed the order in TX /SAPAPO/PPT1.
But as I mention before, user A did not perform any changes to the production order instead user X doing planned order for the low-level code in /SAPAPO/PPT1.
The production order X date and time with status 'REL' and PP-firmed has been resheduled.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.