Events not scheduling while using 'Schedule' option in COMPXPD transaction

Former Member
0 Kudos

I am trying to use the 'Progress Tracking' feature available in SAP ERP Project System. All the necessary configurations have been done to use a progress tracking profile to track the progress of networks, but all i am able to track is the data provided by the user manually using the transaction. The 'Schedule' feature doesn't schedules the events using the scenario.

It also shows the information 'Field Expediting Object is hidden. Value could not be copied' when i am trying to change/define the Scenario in the 'Components' section.

Can anyone please guide as to how the events can be scheduled (dates are populated) automatically using the Schedule feature.

Thanks in advance.

Regards,

Yasmeen Arshad

Accepted Solutions (0)

Answers (1)

Answers (1)

MohanDesai
Active Participant
0 Kudos

Hi Yasmeen,

Could you please mention the error message no.?

Regards,

MRD

Former Member
0 Kudos

Thanks for your reply mohan.

The system is not generating any error message at any step. It just displays the Information while changing/defining the Scenario as specified in the snapshot in the previous post.

MohanDesai
Active Participant
0 Kudos

Hi Yasmeen,

Please refer the screen shot for settings;

Regards,

MRD

Former Member
0 Kudos

Thanks mohan.

The Progress Tracking Profile has already been defined in the Customizing Activity.