Events not scheduling while using 'Schedule' option in COMPXPD transaction

Former Member
0 Kudos

I am trying to use the 'Progress Tracking' feature available in Project System. All the necessary configurations have been done to use a progress tracking profile to track the progress of networks, but all i am able to track is the data provided by the user manually using the transaction. The 'Schedule' feature doesn't schedules the events using the scenario.

It also shows the information 'Field Expediting Object is hidden. Value could not be copied'

Can anyone please guide as to how the events can be scheduled (dates are populated) automatically using the Schedule feature.

Thanks in advance.

Regards,

Yasmeen Arshad

Accepted Solutions (0)

Answers (1)

Answers (1)

jude_bradley
Active Contributor
0 Kudos

Hello Yasmeen,

This is the sapgui forum,

It's not the correct forum to raise a message such as this.

regards,