mile stone confirmation

Former Member
0 Kudos

Dear Experts,

What is mile stone confirmation in sap pm.

what configuration settings to be done to achieve this.

Clients are insisting for mile stone confirmation.

Sheshu

Accepted Solutions (1)

Accepted Solutions (1)

paul_meehan
Advisor
Advisor
0 Kudos

Hi,

In PP you can define a operation as a 'milestone operation'. When this operation is confirmed, all the preceding operations are also automatically confirmed.

Unfortunately this functionality is not available for maintenance or service orders. There is no configuration in PM that can enable this feature.

-Paul

Answers (1)

Answers (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Sheshu,

Milestone confirmation can be performed in PS module. You could define milestones in a project and use them for tracking progress and billing. However, short of integrating PS and PM, it is not available for Plant Maintenance.

I'm not exactly sure what your client requirement is, but in PM confirmations are made against Order operations and that is about the extent of it.    

Former Member
0 Kudos

Dear Paul & Sebastian,

Many thanks for you answers.

He want similar like PP.

Client has agreed with your explanation.

Once again thanks.

Sheshu