on 09-26-2012 7:38 AM
Hi Experts,
We are implementing SNP for one of our client. Our process is something like this: We have 2 DCS, 1Virtual Location in the middle and 1 Vendor which is a simple SC network. The distribution center send the demand signal to Virtual location and Virtual inturn would raise single Purchase Req on the vendor for the demands raised by DC's. But the requirements here is Virtual location Should raise 2 purchase requisions on the vendor per Dc to cover the demand. But, Hueristics raise a single purchase Req on the Vendor. Please let me know is there anyway to infuence Heuristics engine to raise 2 PR on the vendor.
Idea of creating 2 Virtual location is not allowed . Please post an update soon.
Lakshmi.
Hi Lakshmi,
Due to the presence of virtual location in your SC network, the demand from DCs are consolidated and a single proposal (external procurement order) is generated. Since there is a t.lane between virtual location and plant, the proposal will always be a STR.
Probably, for the products in context, you can exclude virtual location and delete product specific t.lanes between DC and virtual locations. Then, execute the SNP location heuristics for DCs only. It will generate individual PR for each DC. If the procurement should be vendor specific, then you can create a t.lane between DC and vendor, but it will create STR instead of PR.
Thanks,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Lakshmi,
One possible way could be executing network heuristics twice i.e. first run considers DC1, VL, and Vendor and the second run considers DC2, VL, and vendor. However, if you have multiple DCs in the network, this is not practical as you have to run the heuristics for each DC.
Another alternative is to use PP/DS with characteristics (to differentiate by DC). But, it's not as simple as SNP heuristics.
Probably, you may need to reconsider your business requirement as well as solution design based on APO limitations.
Thanks,
Rajesh
Hi Lakshmi,
From APO side, it's quite straight forward and SNP generates individual proposals. However, before publishing these proposals, you need to change the source of supply (i.e. replace the APO specific VL plant with the one that exists in both APO and ECC) through customization (either Z program or user exit implementation e.g. APOCFPEP).
Thanks,
Rajesh
Rajesh and Laxmi,
The original request has "some" elements of a make-to-order / pegging scenario so isn't there anything in regards to individual / collective requirements (like the "individual requirements possibe") flag in APO?
Alternatively, CTM plan demand by demand but has it been completely ruled out?
Just curious.
Hi Sap Apo,
We can't use MTO strategy in this case as it needs to collect the requirements (MTS) per DC and then generate a proposal. If we treat the DC as customer, it make sense to consider CTM with MTO. However, other functionality like stock transfers might adversely be impacted and the solution might not be practical due to sales orders (instead of sto) etc.
I might be wrong also as we have 'n' different ways to solve a problem depending on the problem context and constraints. Probably, Lakshmi can add more details.
Thanks,
Rajesh
Hi Sap Apo,
Thanks for your post. CTM is basically order prioritization planning tool and does not support Fairshare concept hence we use heurisstic as our solver . More over, We dont deal with concepts like demand priorization and supply categorization in our business.
Coming to Individual and collective requirements selections in the product location master. I have not explored much, please through some light on how that be useful in our business case.
Hi Rajesh,
I have couple of questions, please let me know if you can provide some inputs.
Q1: Our business is using customized number ranges for purchase requisitions raised from virtual plant to Vendor. There is a business logic the way the numbers being maintained that way. Can we CIF those number ranges from R/3 to APO?
Q2: Is there any enhancement available to change source of supply before publishing to R/3 ?
Lakshmi
Hi Rajesh,
Thanks so much . Not exactly CIFing number ranges from R/3. They wanted a particular number range which is customized number range for the Preqs raised out of VL onto the vendor. Is there any possibility of that sort?
Q2:As discussed with you, Business agreed to create VL2 in APO but not in R/3. What I'am planning to do is that, a custom enhancement that changes VL2 into VL1 that exist in both R/3 and APO before results posted to R/3. Hence PRs created in APO go into R/3 as VL1.
Additional Input from you required is that, We are using Make- to- Stock requirement strategy for our business. The requirement is that Sales orders & Deliveries should consume forecast. I made required configurations to the categoru group etc.. but still I dont see the efffect in the PB. Please provide some info to fix this phenomenon.
Lakshmi.
Lakshmi,
1. APO number range is specific to that box whereas ECC numbers have high precedence i.e. when you PReq transfer takes place, the APO PReq numbers are replaced with that of ECC orders. If you still concern about the requirement, probably, you can define a custom number range using t.code SNRO and assign it to SNP orders appropriately. Typically, we won't go that far in APO.
2. With respect to PReqs generated from VL2, I guess it would be a good idea to delete the proposals after successful transmission to R/3 so that you won't find any differences between ECC and APO. The published PReq come back again to APO with ECC numbers and visible from location VL1.
3. Check the requirement strategy of your product. To support forecast consumption, it should be 20 (t.code /SAPAPO/MAT1, Demand tab, Proposed Strategy field). You can also verify the forecast consumption in product view (/sapapo/rrp3).
Thanks,
Rajesh
Hi Lakshmi,
As mentioned below, A production version must be defined in the material master record (MRP 4).
http://help.sap.com/saphelp_scm70/helpdata/en/68/f3593b0972fa72e10000000a11402f/frameset.htm
I always use a PV in my samples.
You get a warning message when adding PV to a subcon material in MPR 4, but you can confirm it by
pressing Enter again. SAP Note 565024 is also useful for PDS.
Best regards,
Tiemin
Hi Lakshmi,
Happy to note that it worked finally.
Since your orders are simple PReq without using any features typical of subcontracting, a dedicated planning book and data view are not necessary. It will also be helpful for planners, otherwise they need to move between different screens. However, the better answer could be - 'IT DEPENDS' .
Thanks,
Rajesh
Hi Rajesh,
We have another issue now..The PDS is not exploding in the planning book. The demand generted for the primary item is not passing down to the child items. We have different suppliers for header as well as for child items. All prerequisite settings have been maintained. when given the selection by PDS name in the planning book, it picks the PDS but gives an error message saying that there is a conflict reading the slection and planning KF. Please suggest a fix.
Lakshmi.
Hi Lakshmi,
When I follow the SAP online help and note 565024 to build up a subcon sample, it works.
Another point is, I always use the standard PB 9ASNPSBC. To the most, I make a copy of it but won't change any settings.
So instead of repair, please restart from scratch by following the instruction step by step and yours should work, too.
Best regards,
Tiemin
Hi Tiemin,
Thanks of for your reply. I use a copy of 9ASNPBC planning book too. Business categorically mentined that they dont use Production version in their planning. These materials kind of customer BOM available at DC. Manufacturing plants dont come into our scope of our planning. These PDS components are sourced externally no internal manufacturing.
I maintained Dummy Work center, Dummy Prod Version but PDS did flow into APO but dependent demand is not generated.
Please share some thoughts.
Lakshmi.
Lakshmi.
Hi Lakshmi,
Out of the scenarios listed there, which one are you using?
Or can you map your requirements into one of the scenarios there?
I think it should be Subcontracting with Third-Party Provision of Components in SNP
Best regards,
Tiemin
Hi Tiemin,
Yes, Our scenario is similar to Subcontracting with 3rd party provision. But the question did not mention there was " How the BOM header+components flow into APO without a Production version". Do we really require it? You moentioned , you followed all the steps mentioned there for subcontracting PDS. Did you maintain Production version for your PDS?
I have made relevant settings mentioned there but for some reason the BOM is not flowing into APO and not getting exploded and dependent demand is not generated.
Hi Lakshmi,
Outgoing Quota Arrangements may help: http://help.sap.com/saphelp_SCM700_ehp02/helpdata/en/f8/a57539d49e3d35e10000000a114084/frameset.htm
Best regards,
Tiemin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tiemin,
when try to run Heuristics using /SAPAPO/SNPO1 the Heuristic run is successful and but planning results are not published in the planning book. But interactvely it is not doing anything.
Heuristic run is not generating any Purchase req or planned orders only generating STR.
Lakshmi.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.