Schedule Lines are not updating

Former Member
0 Kudos

Dear All

Kindly let me know why schedule lines are not generating in Schedule agreement, here even MRP Run also done,but schedule lines are not getting.

Regards

Rushiker

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member184701
Active Contributor
0 Kudos

dear, what is your schedule line category? regards,

Former Member
0 Kudos

Hi, sorry i am not able to guess where it is, my document having agreement type is LPA and MRP type is P1,

Former Member
0 Kudos

sorry Mr.PPIO i am wrongly posted its MM issue .

former_member184701
Active Contributor
0 Kudos

okay, i agree - that looks like mm question.

please make sure:

1. your MRP type is PD and lot size EX (your material master record)

2. you have a source list record for your sched. agreement item and set indicator for relevance to materials planning to 2

3. you do release of your agreement correctly

regards,