on 09-21-2012 8:16 AM
Greetings!!
I have created a PS project from Portfolio item using a template. Project definition is created in PS (R3). Now i try to transfer the financialy planning data (planned values) using Transfer to SAP ERP system flashes the message "No planning element assigned to item"
Also under the "Related objects" tab the object number and name is not visilbe though the PS project was created on save and it exists in R3.
I might have missed some customizatoin here. Any suggestions pls.
Thanks
Saurabh
Hello Saurabh,
I'm having the same issue myself. Did you get to solve it?
I'd really appreciate some help.
Thanks,
Anna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Additionally you can also refer to the help link below.
Dear Saurabh,
Could you please help me what DFM object links you have maintained ? I am getting same error.
I have Portfolio Item integrated with cProject and from there I have created PS Project and set the status to Released too.
In Financial Planning I ma getting the same error like you.
Regards,
AP
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.