HI Expert,

Scenario is system have all kind of planing in sap ps as

  1. easy cost planning
  2. unit cost planning
  3. detail cost planning
  4. network cost planning

can we use all planning simultaneously?

if no then which-which one cost planning we can use simultaneously in sap ps?

how to control duplicity planning cost in sap ps what should we need to do for the same?

if we are using ECP then we need to an extra CO version so program would be same only need to rename to co version only please correct if i'm wrong.

Regards,

Sanjeev

replied

Here you want to say i need to create separate version for all costing planing

for detail cost planning and unit cost planning you are saying you will get option for choose version here (if didn't create version for all create only 000 & 001 OR need to create for all costing) if i choose version 000 which already using by network costing planing. and 001 for ECP.

in that case plan cost would be duplicity so how to control duplicity?

Which cost planing is more suitable for customer project??

Which cost planing is more suitable for invesment project??