on 09-21-2012 4:30 AM
Hi Experts,
We do have maintained budgets at Level 4, similarly commitments and actuals are also maintained at Level 4. However, the management have now decided to have the Budget control at Level 1.
I know the remaining budget at Level 4 can be extend to Level 1. However, I want to know if I follow following steps, whether I can take the entire budget upto Level 1.
Please do let me know your thoughts on this.
Regards,
MS
Hi Mark,
There is nothing much to do, just go to CJ32 and remove budget from all the WBS except the 1st WBS element.
Thanks,
Soubhagya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
aprat of above
just run CJ32 and remove budget from all the child WBS, Except the 1st WBS element.
whenever you will create PR or any other commitment system take budget from 1st wbs element let say budget controlling and budget release disburse would be on PD level. even budget availability check (AVAC) would be at 1 level of wbs if avac would be active.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi MS,
You can make changes as specified above.
But before that make it sure that you do not want to use previously budgeted WBS i.e. level 4 WBS for raising a new PR of by other means to post actual or commitment.
You have to create new WBS parallel to WBS of level for creating commitment or actual at level 4.
Reason- Following above steps will make distributable amount for previously budgeted WBS of level 4 equal to assigned values.
Run a test cycle in quality/testing server.
Note- system check for budget at child WBS if available then ok else if concern WBS is non-budgeted(No AVAC) then it check parent WBS for budget and so on.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mark,
I think you can achieve the same in a more easier way:
I hope, in this way you would be able to maintained all budget at level 1 along with the control settings you have maintained there.And due to unavailability of budget at 4th level no budget related transaction will occur there .
I hope this helps.
Regards
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.