cancel
Showing results for 
Search instead for 
Did you mean: 

inspection point

Former Member
0 Kudos

how to create inspection point when we use qm with pp.i am assigning inspection points to some operations.during confirmation whether i had to do operation wise confirmation or can i do order confirmation.if i done order confirmation if at any operation the material is rejected what is th

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi,

During the in-process inspection , u need to create the sampling procedure w.r.t freely defined inspection point, need to maintained the inspection at routing or master receipe header, and use proper control key. now if u want confrimation of prdn qty. via QM then put yield or scarp during lot closure other wise go through PP order confirmation.

regards

former_member208199
Active Participant
0 Kudos

Hi Venkateswararao,

Please check the below given steps, first one will help in creating the Inspection points and second one will help in confirmation process with inspection points and its operations.

Inspection point creation:

1) http://help.sap.com/saphelp_46c/helpdata/en/b5/c4db38a91b11d1bd610000e829fdb3/content.htm

Recording the Inspection point confirmation:

2) http://help.sap.com/saphelp_46c/helpdata/en/18/4386c0449011d189420000e829fbbd/content.htm

Please check and revert back.

Thanks