on 09-19-2012 10:17 AM
i want a report that should display the details of actual budget consumed against the WBS, just like when we run Tcode:S_ALR_87013558 and select GOTO>>Line Items>>Project commitment line items and we get all the break-ups for commitment budget with matching figures.
However same options is not available for details of actual budget consumed with matching amount figures. Is there any option for this requirement??how we can get the details for actual budget consumed against any WBS??
Hi Prem,
You may close the thread if you issue is resolved now.
Regards
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prem,
Ankur's reply is more than enough to fulfill your requirement.
In S_alr_87013558, select actual value and navigate Goto->Line item.
Here you will find exact breakup.
Please search forum before posting a query.
You might get the solution instantly.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Pranav,
In S_alr_87013558, when we select actual value and navigate Goto->Line item, here the break up dosnot not match with actual budget figure and not able to find exact break up, thats why i post this issue.
and in table COSP/COEP (Value type 4 & 11) also , it doesnot match with actual budget as in tcode S_alr_87013558
and for your kind information , i already searched this in forum before posting this query but didn't get any suitable solution.
if you say i can send you the screenshot.
Hi Pranav:
You can check note Note 961186 - Differences between totals values and line items
Report S_ALR_87013558 takes its information from RPSCO table, you can check it if your information stored is fine. ( If you think it is not fine I think there is a report to regenerate this table) let us know.
Regrads,
Sara
Hi Prem,
If you could not remember the report name provided by Sara, you could use the menu path below:
CJ30 -> Menu -> Extras -> Availability control -> Analysis. This will have same result as the report BPFCTRA0. You may see the SAP note 178837 how the assigned value is contributed and the AVAC check is trigerred.
Regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prem,
I hope you have applied the same process (Goto->Line items) for Project Actuals in S_ALR_87013558 report. If not, try it.
Alternatively, use standard t-code CJI3 to check the project or WBS actuals.
OR
you can create or develop your own customized report for the same.
Important Tables: For commitment :
COOI (Value type 21 & 22 for PR & PO respectively)
COSP/COEP (Value type 4 & 11)
You can also use SQVI query to develop such a report.
Useful Links:
http://scn.sap.com/thread/3195706
http://scn.sap.com/thread/879416
Hope it helps.
Regards
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.