cancel
Showing results for 
Search instead for 
Did you mean: 

Regarding- Changing Requested Delivery Dates at Schedule Line Level

former_member196521
Active Participant
0 Kudos

Hello All,

I have searched the forum and also read on some of the posts posted on availabilty check, customer requested delivery date, however as per customer requirement

If a sales order consists of two line items and for each one of them the customer requires two different delivery dates, then I put the requested delivery dates in the header which got copied to both to the line items, next when I went to the line item of one of the items the system allowed me to change the requested delivery date however the second line in the schedule line should now get calculated based on the changed delivery date given by the customer, however that is not changing, I tried to rerun availability check also but the system proposed delivery date does not change, could anyone let me know if this date does change and if yes how?

Kind Regards

Atul

Accepted Solutions (0)

Answers (2)

Answers (2)

Lakshmipathi
Active Contributor
0 Kudos

Ensure that once you changed the requested delivery date in the second line item, you hit the "Enter" key.  Without hitting this key, if you just check in schedule line, no changes will happen.

G. Lakshmipathi

former_member196521
Active Participant
0 Kudos

After changing the requested delivery date in the schedule line level, I have pressed the enter key however the system proposed date does not change, please advice further.

former_member223981
Active Contributor
0 Kudos

Can you provide screenshots of the steps that you are taking?

former_member196521
Active Participant
0 Kudos

Hi Noel,

Please find the same attached.

1) Creating the sales order for two line items, customer wants different delivery dates for both line items and the sales order should be the same, as per the system the requested delivery date is entered in the header as shown below.

Next as per customer requirement I am changing the customer requested delivery date for the second line item in the schedule line category

Now I am pressing enter the second schedule line which is the system proposed schedule line category is not changing it remains the same, screen shot attached, ideally this schedule line also should get changed based on the lead times which are proposed from the material master.

As a result of which the system proposed delivery date does not change again in the schedule line category

Kind Regards

Atul

former_member223981
Active Contributor
0 Kudos

Initially, you have a requested delivery date = 27th September. However, the system cannot confirm on this date as there is no available quantity. Therefore, the system confirms for 10th October [you would need to view the ATP overview in CO09 to see why this is the date with an available quantity]. The second schedule line is created because there is no availability on 27th Sept but there is on 10th October.

When you change the requested delivery date to 30th September, the system executes the availability check again [you can see this as the availability control screen is called]. However, there is no available quantity before 10th October. So the system leaves the second schedule line at 10th October [i.e. the system determines 10th October as the nearest date with an available quantity]. This is the correct system response. If you want the system to change this date, you need to add stock or create a receipt earlier than 10th October....

Hope this helps.

former_member196521
Active Participant
0 Kudos

Hi Noel

Thanks for the detailed reply appreciate the same, I have one query when the date is changed from 27th Sept to 30th Sept as per the lead times defined in the material master the second date should also change which is 10th October as per the system the same should change to 13th October, since there is no stock available, however if I do a goods receipt before 10th October then the system will throw a date before 10th Oct, my query is after doing the availability check the system should propose a date after 10th Oct.

former_member223981
Active Contributor
0 Kudos

Please post screenshot of CO09.

former_member196521
Active Participant
0 Kudos

Pasting the same for your reference.

Kind Regards

Atul

former_member196521
Active Participant
0 Kudos

please let me know if you require any further screen shots of CO09

former_member196521
Active Participant
0 Kudos

Noel,

I had raised this issue with SAP, pasting the reply.

this can be the case but it must not be.

When the system caries out a forward scheduling then it can be also

the case that the confirmed delivery date will not be postponed.


Let us assume you have maintained a transit time of 3 days.

The requested delivery date is 15.10.2012 and the end of the

replenishment lead time is on 20.10.2012.

The system first carries out a backward scheduling. The material

availability date is determined on 12.10.2012. So this date is in the

past. Therefore the system starts a forward scheduling from todays date

and determines all other dates. So this means the material availability

date is set to todays date. ATP check determines that today nothing is

available and so the material availability date will be set to the end

of the replenishment lead time. So MBDAT is on 20.10.2012 and the

system carries out a forward scheduling from 20.10.2012 and determines

the new delivery date on 23.10.2012 (3 days transit time).


When you change the requested delivery date to 18.10.2012 then nothing

will happen. The material availability date will be still on

20.10.2012 and so the delivery date on 23.10.2012.


When you keep this situation and you carry out a new atp check tomorrow

then the situation will change. Tomorrow the end of RLT will be on

21.10.2012. It is always shifted. So the material availability date

is on 21.10.2012 and the delivery date will be on 24.10.2012.

Kind Regards

Atul

former_member184701
Active Contributor
0 Kudos

dear,

what is your schedule line category ?

regards,

former_member196521
Active Participant
0 Kudos

Hello,

Copied the standard schedule line category CP to ZP.

Kind Regards

Atul

former_member184701
Active Contributor
0 Kudos

are you able to show the screenshot of VOV6 for your ZP category?

former_member196521
Active Participant
0 Kudos

Screen shot attached below for your reference.

Kind Regards

Atul

Former Member
0 Kudos

Have you tried this?

Select particular line & then go to item conditions-->schedule lines.

hope it will works.

former_member182378
Active Contributor
0 Kudos

mr. PPIO,

Could you please explain why you are looking in to schedule line category?

(if delivery date is not changing)

former_member196521
Active Participant
0 Kudos

Hi Siva,

I have tried this however it does not change.

Kind Regards

Atul