on 09-18-2012 9:41 PM
Hi Gurus,
I'm working with manual planning directly at the portfolio item. The views and categories are already defined, however, the values do not appear at the Financial Summary (I tried to run /RPM/FIN_PLAN_INT, but it doesn't work.
I tried to do the same to another portfolio item which planned values are coming from Project System, but it is not working too.
Can you help me, please?
Thanks in advance.
Regards,
Claudia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Claudia,
All my financial views that have configured 'Amount type' have item process ( I - Integration) , I have not tested your case ( M - Manual) but I think table /RPM/ITEM_D_DER should be filled without execute any report ( in your case).
Could you check to link your 'Amount type : Budget' to another view that is configured as (I-Integration) and execute reports?
Regards,
Sara
Hi gurus,
Thinking about the scenario without ERP integration. We created a portfolio item and planned values directly (we defined a view named "Forecast Costs - Portfolio Item" and assigned the amount type "1-budget").
Throught "SE11", view /RPM/V_FIN_PLAN, we can see budget values correctly planned.
However, the table /RPM/ITEM_D_DER doesn't show any value as "Total Budget" or "Annual Budget".
I already tried to run the reports bellow, but it doesn't work.
/RPM/PLAN_INT_PREP
/RPM/FIN_PLAN_INT
RPM_UPDFI01
Do you have any idea what can be wrong?
Regards,
Claudia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Claudia,
Try running this report & check, "rpm_updfi01". And as Sara has suggested you also need to assign the Amount type as "Planned" for the View you defined..
Rgrds,
Santhosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Claudia,
This is configured in 'Define Financial and Capacity Views', for each view you see 'Amount type', depending on this amount type you can show it in the Financial summary.
Regards,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Claudia
You can check if there are missing customizing entries under
'Define Financial Planning Settings'
for "Map Fin/Cap Entities to cProjects Rate"
and "Map Fin/Cap Entities to cProjects Rate".
Also check the Destination
The logical system name should be maintained as the value for the 'Destination'
SPRO-> Collaboration Projects-> Connection to External Systems
-> Accounting Integration-> Define Object Links for Accounting
Integration
Run the report /RPM/FICO_INT_PLANNING in the SAP-PPM system to
transfer costs to the Financial view
Hope this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Gerry.
Thanks for you answer. The integration is working correctly. Values planned at the project (PS) are transferred to the financial view.
The problem is that although the financial view is filled, the vallues are not summarized at the Financial Summary view. I am sending you screen prints bellow:
Do you have any idea about what the problem is?
Thanks again.
Regards,
Claudia
Hello Gerry.
Thanks for you answer. The integration is working correctly. Values planned at the project (PS) are transferred to the financial view.
The problem is that although the financial view is filled, the vallues are not summarized at the Financial Summary view. I am sending you screen prints bellow:
Do you have any idea about what the problem is?
Thanks again.
Regards,
Claudia
Hi Claudia
Check the configuration if you have maintained the correct
varsion of value type while configuring for Financial and Capacity
Planning integration.
1) SAP xApp Resource and Portfolio Management (SAP xRPM) -> Base System
Interfaces -> Financial Planning Settings
2) SAP xApp Resource and Portfolio Management (SAP xRPM) -> Base System
Interfaces -> Capacity Planning Settings
Please set the required versions for the value type, you want to
transfer to financial and Capacity planning of the item.
Then run
/RPM/FIN_PLAN_INT and /RPM/CAP_PLAN_INT and then /RPM/SET_ITEM_ICONS to
get the correct Fin/Cap Plan overview in Item.
I hope this is of more assistance
Ger