on 09-16-2012 9:57 AM
Dear expert,
Iam using SRM 7.0 EHP2, central contract fucntion. When distributing a central contract to ecc system (ecc 6.0 EHP6) using PI, I found an error in ecc using tcode SXMB_MONI: "Enter a unit of measure". Could anyone give some advice to help fix this issue?
Thanks very much and best regards.
Meng yang
This issue has been fixed. We need to map the srm to ecc conditon.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Are you creating contracts for material or material group ?
please attach contract item data here . what is the UOM for material.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
What is the equivalent UOM in english ?
What is the master data 3000000020 Basic UOM and Order unit UOM in ecc?
Is there any purchase order already exists for this material 3000000020
Note 1757826 - Frequency cusotmizing allows non-existing unit of measures?
If you have maintained UOM in SRM Central contract, check if the ISO code is maintained for the unit in CUNI and if it is the same in ECC.
Only the ISO code is sent in XML.
Regards,
Sushil.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Enter unit of measure when you decide quantity. It will resolve this error.
& if not, you can also check available UOM in SRM. use Txn CUNI.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.