MRP run is creating Receipt too early

Former Member
0 Kudos

I am running MRP Heuristics -SAP_MRP_001.

Demand is in form of Sales order and planning strategy for product is 20 (Planning with final assembly).

I am not able to understand why system is creating receipt earlier.

When I see logs, it shows desired date, which is exactly 16 days earlier than Sales order date. I am not sure from where this desired date is getting calculated.

Can anyone tell how system calculate desited date for MRP Heurstic? 

Please help.

GR/GI processing time, PPDS time fence is Zero days.

Vipul

Accepted Solutions (0)

Answers (2)

Answers (2)

b_valavan
Participant
0 Kudos

Hi,

Check if you have maintained any Scheduling Offset in the Strategy settings.

Br,

BVN

Former Member
0 Kudos

Are you using any Strategy in Strategy.If yes, you can check the settings in terms of Scheduling