on 09-16-2012 12:57 AM
I am running MRP Heuristics -SAP_MRP_001.
Demand is in form of Sales order and planning strategy for product is 20 (Planning with final assembly).
I am not able to understand why system is creating receipt earlier.
When I see logs, it shows desired date, which is exactly 16 days earlier than Sales order date. I am not sure from where this desired date is getting calculated.
Can anyone tell how system calculate desited date for MRP Heurstic?
Please help.
GR/GI processing time, PPDS time fence is Zero days.
Vipul
Hi,
Check if you have maintained any Scheduling Offset in the Strategy settings.
Br,
BVN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you using any Strategy in Strategy.If yes, you can check the settings in terms of Scheduling
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.