cancel
Showing results for 
Search instead for 
Did you mean: 

CJ30 - assigned column in object currency

laimonas_bindokaitis3
Participant
0 Kudos

Hello guys,

I need to have assigned values in CJ30 in object currency. Currently it is displayed in CO area currency, which is not sufficient.

What neeeds to be done for that ?

Thanks guys.

Regards,

Laimonas

Accepted Solutions (1)

Accepted Solutions (1)

former_member195427
Active Contributor
0 Kudos

Hi Laimonas,

                  Proceed as follows:

1. Run T-code OPS9:Budget Profile for projects

2. Select the Budget profile which you have assigned in your project profile while creating the project.

3. Now, at the bottom right of concerned Budget Profile, check  parameters for "Budgeting Currency". I hope, there you have selected the Controlling area currency.Change it to Object Currency and check.

Hope it helps.

Regards

Ankur

laimonas_bindokaitis3
Participant
0 Kudos

your advice worked well, except the checkbox is from availability control subscreen .

Budgetting currency was already selected before. This gives the options for entering budget amounts. Now I selected object currency of availability control, and I have my assigned column in CJ30 in object currency.Thanks anyway !

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Ankur has guided you very well.

Along this use currency field of CJ30 selection screen.

Regards,

Pranav