on 09-12-2012 1:50 PM
Hello guys,
I need to have assigned values in CJ30 in object currency. Currently it is displayed in CO area currency, which is not sufficient.
What neeeds to be done for that ?
Thanks guys.
Regards,
Laimonas
Hi Laimonas,
Proceed as follows:
1. Run T-code OPS9:Budget Profile for projects
2. Select the Budget profile which you have assigned in your project profile while creating the project.
3. Now, at the bottom right of concerned Budget Profile, check parameters for "Budgeting Currency". I hope, there you have selected the Controlling area currency.Change it to Object Currency and check.
Hope it helps.
Regards
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
your advice worked well, except the checkbox is from availability control subscreen .
Budgetting currency was already selected before. This gives the options for entering budget amounts. Now I selected object currency of availability control, and I have my assigned column in CJ30 in object currency.Thanks anyway !
Hi,
Ankur has guided you very well.
Along this use currency field of CJ30 selection screen.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.