Alternate BOM 2 is required in production order

Dear Experts

I have two alternate BOM for one vehicle , alternate BOM 1 and alternate BOM 2. When i create production order for that vehicle it take the alterante BOM 1 by default, but i want to create this production order with alternate BOM 2. Please guide how it is possible.

Regards

Parkash Chand

replied

Go to MM02 >> MRP 4 (tab) >> make Selection method    =  1

Go to OS32 >> Enter material, plant, BOM usage, date (some time before basic start date) , Alt BOM = 2

Save it.

Create production order and go to your master data tab.