Hello All,

Using the TAXINN procedure, for my condition type JEXP the condition record is maintained in the access Country, Plant, Control Code(Chapter id) I have also maintained J1ID settings which is linking of the chapter id to the material, however when I am creating the sales order the condition type for BED which is JEXP is not getting calculated, I have checked my pricing procedure and also checked the from and too step the step above it is a subtotal step just for calculation purpose.

When I went to analysis and checked the access where I have maintained the record the system says that no chapter id is maintained for the same, however when I check the j1id for that particular material the chapter is maintained. Do let me know what could be the possible cause of the missing condition type.

Kind Regards

Atul

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

I have also maintained J1ID settings

For TAXINN, this is not required.  Ensure that the required tax code is assigned to that condition type in FV11 / FV12.

G. Lakshmipathi

former_member196521
Active Participant
0 Kudos

Hi Lakshmipathi,

Could you elaborate further when you say assign the tax code to the condition type in FV11, the tax condition JEXP was getting triggered earlier in my sales order without the setting which you have mentioned above in your post.

Kind Regards

Atul

Former Member
0 Kudos

Dear Atul, 

are you getting the c-type?

if you are getting the c-type in conditions tab then check JEXP and go to c-record, here u can get from which record the data is fetching

and then go to  analasys check all the tables in that c-type.

Regards

Raj

former_member196521
Active Participant
0 Kudos

Dear Raja,

Thanks for your reply, I am not getting the condition type in my sales order, however when I go to analysis of the condition type in my sales order, and go to the particular access( Country, Plant Control Code- Chapter id) it says that the chapter id is missing, however I have maintained the condition record in vk12 for the particular chapter id and also maintained corresponding entry in J1ID tcode as well.

Also the message in the analaysis says Access not made

Kind Regards

Atul

Former Member
0 Kudos

Dear atul,

plz share the screen shot of pricing analasys.

Regards

raj

former_member196521
Active Participant
0 Kudos

Dear Raja,

Please find the same.

In the first screen shot attaching the conditions which are getting trigered.

Attaching the analsysis of JEXP condition type which is not getting triggered.

In the next screen shot I am attaching the condition record which I have maintained for condition type JEXP.

Next Attaching J1ID settings.

Kind Regards

Atul.

Lakshmipathi
Active Contributor
0 Kudos

the tax condition JEXP was getting triggered earlier in my sales order without the setting

I dont know what settings you had but I can only say that if you maintain in FV11, system will fetch into your sale order.

G. Lakshmipathi

former_member196521
Active Participant
0 Kudos

The condition type JEXP which is for sales is not defined in FV11.

Former Member
0 Kudos

Hi Autl,

As per my understanding Why do't you check Material master  Foreign trade tab control code.

Regards

Siva krishna

Former Member
0 Kudos

Dear Atul,

plz share pricing procedure screenshot.

former_member196521
Active Participant
0 Kudos

Dear Raja,

Please find the same attached.

Kind Regards

Atul

former_member196521
Active Participant
0 Kudos

Hi Siva,

The chapter id is maintained in material master data foreign trade data.

Kind Regards

Atul

former_member196521
Active Participant
0 Kudos

Hello All,

Can see JEXP analysis given below.

reason behind this was

If you go to the Analysis part within pricing in these sales order

you may see that the status of the Accessable Condition (ZASS) and BED

(JEXP) has status "Condition record exists, but has not been set" and

this usually happens when you do some changes in Price master related tothat document or some other changes on which pricing is based, in such

cases you need to update the pricing once.


Kindly follow the below steps and you may see JEXP in all the three SO


Go to T-code VA02 --> Go to item level --> Select Condition --> Select

update button and select option "C"

Kind Regards

Atul