Hello Gurus,

I have a question: is deadline monitoring with events(WF_APPR_LATEST_START and WF_APPR_REQUESTED_END) also with application controlled workflow possible? We use n-step badi and we would like to activate notifications and alerts.

Thanks a lot

Ralph

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Dear Ralph,

Please check the following documentation about SRM notifications and deadlines:

http://wiki.sdn.sap.com/wiki/x/CgaYDw

I hope this will help You!

Best Regards,

Gergely

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Ralph,

Deadline monitoring with events is not applicable to AC WFL.

For AC WFL you can trigger alerts by setting deadlines directly on the tasks and using the

SWWDHEX  deadline job. The deadline text is taken from the work item. The work item text is maintained in the step of the workflow in the builder (Transaction SWDD). The recipients are also maintained in the step.

Cheers,

Melina

PS.: If this helps you, please assign the concerning SDN points