We are manually setting conversion indicator for planned order which is having both start and end date in PAST . In ECC i am able to see production order in PAST and operation having status of TIMEX . I hope this is std SAP functionality since APO will decide the date .
Even this order comes back to APO with dates in the past . SAP std int strategy profile is not rescheduling this order even i tried with current date scheduling but its not rescheduling those production order. is it std behavior?
But we dont want to create production order in the past . How we can restrict this behavior. Is there any standard settings to restrict this in APO & ECC side.
i am thinking of below options.. but i am not sure whether this will help
APO side :
1) using customer exit in conversion rule ( while conversion we can restrict orders in the past)
2) by using outbound user exit in APO side
ECC side:
1) During the inbound we can validate order start date
2) if possible we can reschedule before saving production order. so that order can be in current date
Please some one guide.. which one would be best idea for this.. or is there any other way we can stop this behaviour or reschedule this production order order to current date
Regards
Rajesh
Hi Rajesh,
You can have a look at note 394113.
There is a field "Scheduling Offset" in strategy profile. If it contains a minus value, the order can be in the past.
BR,
Tiemin
Message was edited by: Tiemin Wang
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajesh,
Since you are manually processing these orders with past dates, i assume that there are very few orders of this kind. I would suggest to reschedule the order with DS planning board (select the order and reschedule) and then convert it from DS board itself. Anyway it is manual processing only, so this should not cause much trouble to you.
regards,
Sreeram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi rajesh,
I hope orders created in past will be rescheduled in APO through SAP std integration strategy profile(SAPINTR) when its comes back to APO from ECC.
Regards
Arasu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.